Buying Policy
Average commitment lead time for Capital Expenditures decreased in December by eight days to 132 days. Average lead time for Production Materials increased in December by two days to 69 days. Average lead time for Maintenance, Repair and Operating (MRO) Supplies decreased in December by three days to 37 days.
Percent Reporting | |||||||||
Capital Expenditures | Hand-to-
| 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average
| ||
Dec 2020 | 24 | 5 | 10 | 17 | 28 | 16 | 132 | ||
Nov 2020 | 22 | 6 | 10 | 16 | 27 | 19 | 140 | ||
Oct 2020 | 23 | 5 | 8 | 17 | 29 | 18 | 140 | ||
Sep 2020 | 25 | 6 | 9 | 15 | 27 | 18 | 135 | ||
| |||||||||
Percent Reporting | |||||||||
Production Materials | Hand-to-
| 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average
| ||
Dec 2020 | 9 | 33 | 27 | 21 | 7 | 3 | 69 | ||
Nov 2020 | 10 | 35 | 24 | 22 | 6 | 3 | 67 | ||
Oct 2020 | 10 | 38 | 25 | 19 | 6 | 2 | 62 | ||
Sep 2020 | 10 | 36 | 27 | 18 | 7 | 2 | 64 | ||
| |||||||||
Percent Reporting | |||||||||
MRO Supplies | Hand-to-
| 30 Days | 60 Days | 90 Days | 6 Months | 1 Year+ | Average
| ||
Dec 2020 | 32 | 37 | 17 | 12 | 2 | 0 | 37 | ||
Nov 2020 | 34 | 36 | 16 | 10 | 3 | 1 | 40 | ||
Oct 2020 | 34 | 39 | 17 | 8 | 2 | 0 | 34 | ||
Sep 2020 | 35 | 39 | 15 | 8 | 3 | 0 | 35 |