• A key section of Minnesota’s TH 169 in Elk River is being converted into a freeway,
providing faster and safer access to Greater Minnesota.
• WSB was contracted to oversee final roadway and bridge design, and utilized 3D and 4D
modeling for design and construction coordination as well as for delivering paperless plans.
• Leveraging Bentley applications saved 18 months relocating utilities and accelerated the
construction schedule by three months on MnDOT’s first project to use digital delivery
methods.
• WSB’s success was predicated on establishing a connected data environment and digital twin
that has set the bar for the future of 3D modeling, visualization, and cross-discipline project
coordination in Minnesota
You are reviewing the
Download.
Your machine is locate at 18.116.85.111.